The CCC Process Explained: Securing Your Certificate of Completion and Compliance Without Delays

A practical guide to the PSP-led CCC process, the supporting documents and the building checks to complete before an industrial move.

The practical answer

For the applicable CCC regime, the Principal Submitting Person (PSP) certifies the completed building after checking compliance, safety and the required supporting certifications. Prepare the Forms G and agency evidence during construction; treat possession, CCC, fit-out approval and permission to operate as separate milestones.

What does a CCC actually confirm?

A Certificate of Completion and Compliance records the professional certification of a completed building under the applicable building-control framework. For an industrial occupier, the useful question is whether the certificate covers the building and works you intend to use. Physical completion, delivery of keys and a utility account do not answer that question on their own.

The CCC system replaced the earlier local-authority Certificate of Fitness for Occupation system for the relevant newer projects. An older factory may therefore have a CFO or CF record. Ask the project professional or local authority to verify which regime applies; the age of the document alone does not establish a defect. This guide focuses on the workflow commonly used in Peninsular Malaysia. Confirm the applicable state legislation and local procedure for Sabah and Sarawak.

Sources: KPKT — Local Government Department · KPKT

Who issues the certificate?

The Principal Submitting Person issues the CCC within the scope of the professional’s authority. The local authority retains building-control and inspection powers. Appoint the appropriate registered professional early and agree who coordinates each supporting discipline.

LAM’s guidance highlights inaccurate completion of Forms F, F1 and G1–G21 as a recurring problem. A certificate programme therefore needs document review as well as site inspection. Professional appointment, the project’s approval record and the completed building must tell a consistent story.

Sources: KPKT — Local Government Department · Lembaga Arkitek Malaysia · Board of Engineers Malaysia

Step 1: Set an approved-plan baseline

Before construction or a major alteration progresses, ask the PSP to identify the approved building plans, relevant conditions and approved purpose of the premises. Record proposed mezzanines, process equipment, storage changes and other variations before they are installed. A late drawing amendment can affect several disciplines at once.

  • Create a document register linking each approval to its drawing revision and responsible consultant.
  • List outstanding conditions and the person who will obtain each required confirmation.
  • Set inspection hold points in the contractor’s programme rather than discovering missing evidence at handover.
  • Check that the stated factory address, lot reference and building phase remain consistent across records.

Sources: Lembaga Arkitek Malaysia · Majlis Perbandaran Selayang

Step 2: Close the supporting certifications and technical evidence

Forms G1–G21 support the CCC process across the relevant construction and service stages. The applicable forms must be completed by the responsible parties, with agency clearances where required. BEM publishes state forms and guides; the PSP should use the current set for the project.

The technical close-out should follow the building’s actual design. Depending on scope, evidence may concern fire protection, water, sewerage, electricity, access and other services. Arrange testing and inspections early enough to correct defects before the intended occupation date.

  • Maintain a live tracker showing submitted, inspected, rejected and complete items.
  • Resolve incomplete signatures, missing test records and drawing discrepancies before requesting final certification.
  • Confirm actual service readiness; a nearby substation or proposed pipe connection does not prove usable supply to this building.

Sources: Board of Engineers Malaysia · KPKT — Local Government Department

Step 3: Issue, deposit and hand over the completed record

Once the applicable requirements are satisfied, the PSP issues Form F. Form F1 concerns partial completion and needs specific professional and local-authority attention; it should not be assumed to authorise occupation of every part of a development.

KPKT’s OSC 3Plus announcement of August 2026 reminds PSPs to undertake the relevant inspection and deposition workflow through the system. It states that the Form F copy must reach OSC at the local authority within fourteen days of the date on the form. This is a deposition requirement after issue, not a promise that a new factory can obtain its CCC in fourteen days.

  • Request the issued certificate, supporting close-out register and proof of the required deposition.
  • Retain approved drawings, warranties, operation manuals and essential test records in the handover file.

Sources: KPKT — OSC 3Plus · Board of Engineers Malaysia

How to protect the leasing or purchase programme

Build the property transaction around verifiable milestones. During negotiations, identify who must provide the completion documents, which works remain, when access for tenant fit-out is permitted and what happens if the agreed readiness conditions are not met. Ask the legal and technical advisers to align those provisions with the project facts.

For a completed factory in Selangor, Johor or Penang, compare the certificate against the current layout. A later extension or conversion may need separate approvals. Also confirm planning use, the business or premises licence, manufacturing requirements and process-specific permissions. A building certificate alone does not establish all of these.

  • Share the intended machinery, storage configuration and occupation date before shortlisting.
  • Have the PSP identify unresolved technical dependencies and realistic sequencing.
  • Use a written readiness checklist for landlord, tenant, project manager and professional team.

Sources: Majlis Perbandaran Selayang · Lembaga Arkitek Malaysia

Useful answers

Common questions.

Does vacant possession mean the factory has its CCC?

Request the actual certificate and have the project professional confirm its scope. Possession is a transaction milestone; it does not replace verification of the building record.

Can the local council issue the CCC for me?

Under the applicable CCC system, the PSP issues it. The local authority retains oversight and may act where building requirements are not met.

Does a CCC allow my manufacturing process to start?

Confirm the separate planning, premises, manufacturing and process-specific requirements for your operation. The CCC addresses the building, not every permission needed to run a factory.

How long will a factory CCC take?

The programme depends on construction, approved variations, technical evidence and unresolved conditions. Obtain a project-specific schedule from the PSP; there is no reliable universal completion promise.

Read the source

Official sources & further reading.

This guide summarises published requirements and location information. Confirm the current rules, approved use and project-specific conditions with the relevant authority and your appointed professional advisers.

  1. CCC implementation FAQ KPKT — Local Government Department · Accessed 5 November 2026
  2. Guide to CCC forms Lembaga Arkitek Malaysia · Accessed 5 November 2026
  3. CCC forms and professional guidance Board of Engineers Malaysia · Accessed 5 November 2026
  4. CCC deposition announcement, 5 August 2026 KPKT — OSC 3Plus · Accessed 5 November 2026
  5. CCC submission checklist Majlis Perbandaran Selayang · Accessed 5 November 2026
  6. CCC implementation circular replacing the earlier CFO system KPKT · Accessed 5 November 2026
Your next step

Put these checks into your property brief.

Tell us your activity, preferred location, area, power requirement and occupation date. Our corporate property desk can help focus the property search and identify questions to resolve for the selected site.

Discuss your industrial requirement
Your next industrial address

Let’s put your operation on the map.

Leasing, industrial land acquisition and built-to-suit requirements.

Talk to our corporate desk ↗
0 parks in your shortlistCompare parks ↗